| |
|
|
The
Bowdoin College experience with commissioning By
David D'Angelo, Bowdoin College and Clifton W. Greim, P.E., Harriman Associates
A new building usually
means headaches for the facilities department. Once occupants are settled
in, the phone starts ringing and the complaints start coming. Equipment
is noisy. Fans don't work or won't shut off. Rooms are too warm or too
cool. The more complex the building, the more problems — and the more
time the facilities staff must spend to get them resolved.
But that's not what happened at Maine's Bowdoin College. When the $20.5
million, 100,000- sq.-ft. Druckenmiller Science Hall was completed, there
were just a half dozen calls reporting problems -- despite systems that
are especially complex because the building combines several science disciplines,
each with different needs. The reason for the lack of headaches? The decision
to commission the building before move-in.
A before-occupancy trial
Integral
to construction program
Major
building program in progress
--facilities
management department
--computerized
project management
--a
complex building
Differences wth other tests and inspections
Deciding
to commission
--the process
--priorities
--checking system as a whole
Types of problems
--safety issues
--energy wasters
--time wasters
A before-occupancy trial
Commissioning put the building through a "sea trial" before the building
was occupied. Every component of the heating, ventilating, and air conditioning
system was physically checked to make certain that it worked as it was
designed to work. When a problem was found, responsibility for correcting
it was assigned and components were rechecked to verify that the problem
had been corrected.
The methodical, thorough process fine-tuned systems for more efficient
energy use and uncovered mistakes and omissions that might have resulted
in safety and maintenance problems if they had gone undetected. Because
complaints were minimal, the facilities staff could direct their attention
to regular maintenance and operations or the next project. And because
systems were checked thoroughly before the warranty period ended, contractors
and subcontractors were still accessible and responsibility for correcting
problems was clear.
top of page
Integral to construction program
The benefits were so apparent that commissioning is now an integral
part of a $132 million construction program now in progress at Bowdoin.
While not every project will be large or complex enough to warrant commissioning,
it is now a standard line item on the budget forms and is always considered.
At a cost of about 1 percent to 2.5 percent of the cost of the HVAC system,
Bowdoin has found that the benefits outweigh the cost.
And now, Bowdoin has begun to involve a commissioning agent earlier in
the process. Instead of waiting until HVAC systems are built, the agent
joins the team during the design development phase, after concepts and
schematic designs have been approved, but before construction has begun.
This brings another set of eyes to a project at a point when changes can
be made economically if needed. The focus is on the synergism of team
work to find potential problems and resolve them on paper. The early involvement
also makes the commissioning agent more familiar with the project when
physical checking must begin, thus expediting the process.
For its first commissioning project, however, Bowdoin opted to start the
process in the construction phase.
top of page
Major building program in progress Bowdoin
College is a coeducational, liberal arts institution, founded in 1794
in Brunswick, a town of 22,000 on the Maine coast. The college is residential
and nonsectarian and its 1,550 students come from across the country and
around the world. Over thirty-seven departmental and interdisciplinary
majors leading to a bachelor of arts degree are offered.
Over 80 buildings are part of the 110-acre campus. They range from Massachusetts
Hall, built in 1802, to Chamberlain Hall, a new student residence, and
the newly renovated and technologically upgraded Searles Science Building,
both of which were completed in August 1999. Over the past five years,
the college has invested $62 million on capital projects, and planning
for the next five years shows the potential for an addition $45 million.
top of page
Facilities management department
The facilities management department, headed by William S. Gardiner, has
100 employees, assigned to operations and maintenance (trades); facilities
services (housekeeping, grounds, and automotive); finance and property
management; and construction management.
Responsibility for managing construction projects and setting up project
budgets falls to the planning and construction unit within the department.
A construction manager is assigned to each project and provides day-to-day
oversight of the design and construction process.
top of page
Computerized project management
Computerized management processes are central to project management. At
the start of each job, a "folder" is set up in a spreadsheet program.
Continually updated throughout the design and construction process, it
becomes the key document, first for planning, and later for tracking costs
and progress for all phases of the project.
The system has been in place for almost five years and took about two
years to refine to its current form. Within categories such as construction
cost, fees, and owner's costs, a standardized set of line items is included
on the screen when a new job is established. The pre-set line items help
expedite the budgeting process, with a fill-in-the-blanks approach where
categories can be easily added or deleted.
The initial budget is established by the facilities management department
and then submitted to the building committee. Modifications are ongoing
as the projects move through programming and concept, schematic design,
design development, and construction phases.
top of page
A complex building
When planning began for the Druckenmiller Science Hall, it was apparent
that the building would be more complex than many others. The building
would bring together biology and chemistry departments, and though the
HVAC requirements for each discipline were different, they had to be integrated
into one system.
In addition, further complications would arise because the new facility
would be created by constructing the new building and renovating two existing
buildings, tying all three together. The sheer number and interrelationship
of components meant more opportunities for problems in both installation
and operation.
And since the competitive bidding process can lead to a system composed
of components different from those the designer conceptualized, it was
important that the entire system be tested to ascertain that each component
would operate in the right sequence with other components.
top of page
Different from other tests and inspections
Commissioning would put the systems through detailed operational tests,
verifying that all components were working as designed, functioning at
top efficiency, and meeting manufacturer's specifications. Problems would
then be documented, along with identifying those responsible for correcting
the problems. A follow-up check would verify that the correction had been
made.
The standard pre-occupancy inspection would not offer the same level of
thoroughness, detail, and focus. It typically brings owner, designer,
and contractor together, walking through the building, making a visual
check to determine if parts are missing or broken, or whether equipment
and controls are where they should be. Often the emphasis in this type
of inspection is to meet code requirements in time for move-in day, which
is generally very close to the inspection itself.
Testing and balancing procedures, too, would not be as thorough as commissioning,
since they measure air and water flow in HVAC systems. The procedures
ensure that air and water are being distributed in the right amounts to
various spaces, as designated on drawings, but do not check the operation
of controls.
top of page
Deciding to commission
Although Bowdoin had not commissioned a building before, the facilities
department staff decided that the Druckenmiller project would benefit.
Besides the complexity of the systems, the science department wanted Druckenmiller
ready to use as soon as possible to minimize disruption to the educational
program. An aggressive construction program could add to the problems
that might be encountered. As a result, a line item for "commissioning"
was added under "owner's costs."
Although some institutions have their own staff do commissioning, Bowdoin
decided that an outside agent would better serve their needs. Without
a history of cost to use, the construction management department used
the 1 percent figure in the initial budget that was approved by the building
committee -- a figure that turned out to be on target.
top of page
The process
The commissioning process at Druckenmiller would begin as soon as the
mechanical system was completed, but well before move-in. After reviewing
proposals from qualified firms, Harriman Associates, a full-service architecture
and engineering firm in nearby Auburn, Maine, was selected as the commissioning
agent. The firm had provided neither architecture nor engineering services
for the building, a factor that Bowdoin believed was essential to ensure
an unbiased opnion.
Harriman Associates' task would be to put the HVAC system through a four-season
"shakedown." Every part in the system would be physically checked to make
certain that it operated as indicated on drawings and in the sequence
specified. Since operation for some components would differ depending
on the season, commissioning would make certain that Bowdoin would have
no surprises in winter for a building that was completed in summer.
The first step for Harriman Associates was to study the design of the
system and become familiar with its intent. Next, a schedule was set up
to clarify when parts of the system would be commissioned. This required
coordination among owner, contractor, subcontractors, and balancing technicians.
Some parts of the building had to be ready before others so they were
given priority. And before commissioning could begin, subcontractors had
to complete their work.
top of page
Priorities
Among systems given priority for commissioning were thermostatically controlled
exhaust and supply fans, smoke evacuation systems, chiller, chilled water
pumps, greenhouse supply and exhaust systems, fan coil units, air handling
units, air terminal boxes, fume hoods, and pressure controls.
Other systems commissioned were reheat coils, steam-to-water converters,
finned-tube radiation units, cabinet unit heaters, hot-water pumps, heating
coils, humidifiers, and radiant ceiling panels.
Some of the problems found during commissioning and thus corrected, saved
the facilities department time, since their staff did not have to deal
with fixing a problem in-house or with getting a subcontractor back to
do it. Some had the potential to save energy, since equipment was fine-tuned
and ascertained to be functioning as it was designed. And some solved
potential safety issues before they occurred, since they were related
to life-safety codes.
top of page
Checking system as a whole
Despite the fact that contractors and installers had done their jobs well,
without a process to look at how the system functioned as a whole, some
problems may have gone undetected for a long time and some might never
have been found. Some undoubtedly were mistakes, as might be expected
in a project as complex as this one. But many came about because of the
interrelationships among system components and would have gone undetected
without the verification of sequencing that occurs in commissioning.
Documentation is a critical part of the commissioning process. It defines
the problem, indicates when it was found, and designates who is accountable
for correcting it. Once notified that a problem has been corrected, the
commissioning agent then checks again, re-testing the operation of the
components. If everything checks out, the agent notes that in the report.
If it doesn't, that too, is noted and the re-checking continues until
the problem is corrected.
top of page
Types of problems
The time it takes to get a problem corrected can vary greatly. Some are
relatively simple and the contractor or subcontractor responsible can
correct them easily. Others may require numerous follow-ups that stretch
over a period of several months. The following examples illustrate the
types of problems that commissioning can find and the process used to
correct them.
top of page
Safety
issues In educational facilities, life-safety codes require ducts
to have sensors that trigger a series of actions should smoke be detected.
Alarms are usually activated at the facilities department. Dampers close
in return and supply-air ducts to keep smoke from dispersing throughout
the building. Air-handling units are turned off and smoke-purge systems
are turned on.
Testing procedures will be able to ascertain that the individual components
function, but they won't be able to determine that they will function
in the right sequences when it really matters -- during a fire.
Commissioning, however, can provide that assurance. To simulate what would
happen in a fire, a smoke canister can be activated in the duct. As smoke
is emitted, the commissioning agent can verify that alarms, dampers, and
air- handling systems are functioning as they should, and if they are
not, can start the corrective process to ensure that they will.
Areas in which hazardous materials are stored require special attention.
Should a fire break out, a clean-agent suppressant gas is sprayed into
the area from a remote mounted tank. The gas works by removing oxygen
from the air and in essence smothering the fuel. But because the gas removes
oxygen, it is especially important that it be kept from going to other
parts of the building. Dampers in the ducts must close fast enough to
keep the gas contained.
Traditional inspections or walk-throughs will determine whether the damper
will open and close, but without a test of the system, it won't be possible
to know whether they will close fast enough in an emergency. Commissioning
will provide that verification, giving assurances that the system will
function properly.
top of page
Energy wasters Pre-occupancy
inspections will indicate whether a piece of equipment is operating but
they won't be able to verify that it's operating at top efficiency. And
with energy costs high, that's especially important.
And that's where commissioning can help, with its focus on proper operation
of the system. A leak in duct work, for example, can cause the fan in
the related air-handling unit to work harder and thus waste energy. Other
examples include a fan that stays on too long and a damper on an outside-air
duct that stays partially open when it should be completely closed.
In a large facility with several air-handling units and numerous dampers,
checking the physical operation of each is the only way to determine whether
all components are operating in a way that creates top efficiency for
the system.
top of page
Time wasters Commissioning can
also save time for both facilities staff and users of the building. Staff
members can devote time and energy to normal, reactive maintenance, especially
advantageous during a building program involving many projects and an
aggressive time schedule. If the building is no longer under warranty
when a problem is discovered, the institution will have to spend time
making repairs or getting them made. And even if the building is still
under warranty, it is usually more difficult to have subcontractors come
back, especially after they have received final payment, including the
retainment fee. Commissioning saves time for building users, too. By eliminating
most post-occupancy complaints, users don't have to spend time explaining
problems. And that is a side benefit to the facilities staff because positive
feelings about the building tend to continue.
Bowdoin has found
that the tangible and intangible benefits to commissioning more than outweigh
the cost it adds to a project. As a result, the construction management
staff will continue to make commissioning an integral part of its construction
projects — and the facilities staff can continue to count on fewer headaches.
top of page
Written for Facilities Manager, November/December 1999
|
|
 |