| |
|
|
HVAC
trials:
Commissioning ensures that all components in a new system will work
together as designed
By Clifton W. Greim, P.E., Harriman Associates, and David D'Angelo,
Bowdoin College Heating, ventilating,
and air conditioning (HVAC) systems in new and renovated buildings have
become increasingly complex, with hundreds of components that are connected
and interrelated and often controlled by a central computer.
And like the chain with a broken link, if one part doesn't operate as
it should, the effectiveness of the whole system is compromised.
Commissioning is a methodical, thorough process that puts all parts of
an HVAC system through a trial run, giving owners assurance before move-in
that everything works as designed.
It results in energy savings and fewer complaints from building users,
and it often uncovers mistakes and omissions that could result in serious
safety and maintenance problems if not corrected — from duct smoke detectors
that don't respond as they should, to fan motors that wear out too soon.
Why it's needed
--different from pre-occupancy testing
--different from testing and balancing
--starting in design phase
What is checked
--verify proper operation
--proper sequencing
Problems uncovered
Assessing responsibility
Benefits outweigh costs
--safety issues
--indoor air quality
--easier problem resolution
Why it's needed
HVAC systems in the past were relatively simple. With few components and
manual controls, starting up a new system often meant a simple equipment
start-up by a contractor. That's not enough for today's systems. While
they're more efficient and offer greater comfort and better air quality,
they're also complicated. The sheer number and interrelationship of components
mean more opportunities for problems in both installation and operation.
And the typical bidding process offers more. Designers often have certain
products in mind when they conceptualize a system, but rarely specify
proprietary components because of competitive bidding. The system that
is created may consist of entirely different products, effecting subtle
changes in operation that can't always be predicted. In addition, different
subcontractors typically procure and install different components, even
though the components must work together.
Commissioning tests the whole system. It not only makes sure that each
piece of equipment and each control operates properly, but also determines
whether they operate in the right sequence with other components.
Different from pre-occupancy inspections
Commissioning differs from pre-occupancy inspections in thoroughness,
detail, and focus. A pre-occupancy inspection is essentially a visual
check of the building, with the owner, designer, and contractor walking
through, noting problems that must be corrected before move-in. Are any
parts missing? Are equipment and controls where they should be? Are there
any broken parts? The emphasis is often on meeting code requirements in
time for move-in day.
Commissioning goes further and puts the HVAC system through detailed operational
tests. An independent agent, working for the owner, verifies that all
components are working as designed, at top efficiency, and meeting manufacturer's
specifications. The agent documents any problems, suggests who is responsible
for correcting them, and then re-verifies to make certain that the corrections
have been made.
While a pre-occupancy inspection might note that a missing thermostat
should be installed, commissioning would make certain it was calibrated,
that it functioned properly, sending commands to numerous other components
in the right sequence, and that those components responded as they should.
top of page
Different from testing and balancing
Commissioning is also different from testing and balancing procedures,
which measure air and water flow in HVAC systems. While balancing ensures
that air and water are being distributed in the right amounts to various
spaces, as designated on drawings, it does not check the operation of
each component.
top of page
Start in design phase The commissioning
process is often a service provided after a project is completed, but
before move-in, but it should begin during the design phase. The commissioning
agent then becomes a part of the team from the beginning, working with
architects, engineers, and contractors. This allows for a more integral
process, with peer review throughout the design phase. The expertise of
the commissioning agent is available early on, when better solutions can
be effected economically.
top of page
What is checked
In commissioning, the HVAC system is put through a four-season "shakedown."
Every part in the system is physically checked to make certain that it
operates as indicated on drawings and in the sequence that is specified.
If a project is completed in the summer, an owner doesn't have to wonder
whether the heating system will perform properly when it's needed. Commissioning
will have made certain that it will.
top of page
Verifying proper operation
The specific tests performed depend on the project and the systems that
were designed, but a key element is verifying proper operation among components
and the controls that signal them to respond. For example, variable-air-volume
boxes in ducts are checked to determine if they respond as they should
to a command from a thermostat that calls for heat or cooling and whether
air flow for minimum and maximum settings is correct.
Reheat coils in ducts are tested to see if they stage on and off as required.
And speed drives on supply- and exhaust-air fans are checked to determine
if they adjust to varying air flows. To check the smoke sensors in ducts,
commissioning agents sometimes use smoke canisters to determine whether
dampers in the ducts close as they should to keep the smoke from being
further dispersed and whether alarms are signaling.
The commissioning agent also ensures that enough outside air is being
mixed with indoor air to freshen required spaces to meet building codes.
top of page
Proper sequencing Among other components
put to the test are air-handling units, condensing units, classroom unit
ventilators, pumps, boilers, chillers, automatic valves, system alarms,
heating coils, sawdust collectors in wood shops, laboratory hoods, ventilation
systems in gymnasiums and auditoriums, and the computerized energy management
system. They are all checked to be certain they operate in the correct
sequence and are using fuel and electricity efficiently.
top of page
Problems uncovered
The results of each test are thoroughly documented in a report., and an
ongoing punch list is generated. The larger and more complex the system,
the more probable that many deficiencies will be found, as was the case
in a large project involving research labs, in which some 400 problem
areas were spotted.
In a smaller project, deficiencies are generally fewer, but it would be
unusual for none to be found, despite the best intentions of contractor
and subcontractor, who are often hurrying to meet deadlines. The systems
and the interrelationships among components are just too complex.
top of page
Assessing responsibility
When problems are found, the commissioning agent describes them specifically
and suggests who is responsible for correcting them, usually the general
contractor and subcontractors, and, occasionally, the designer. The agent
then re-commissions the system or component after corrections are made
to verify that the problem has been truly resolved.
Sometimes the correction is easily made, as simple as connecting a loose
wire. But for some issues, the fix can be complicated, requiring designer,
owner, contractors, and commissioning agent to work out a resolution together.
top of page
Benefits outweigh costs
The cost of commissioning is usually from 1 percent to 2.5 percent of
the cost of the HVAC system, but owners find that cost is outweighed by
both tangible and intangible benefits. The types of problems found and
corrected range from minor to substantial.
top of page
Safety issues Without commissioning,
even some major problems could have gone undetected until an emergency.
For example, in two recent school commissioning projects, more than half
of the smoke detectors in ducts were found to be deficient and 60 percent
were not calibrated as they should have been. Without commissioning, it
would have been difficult, if not impossible, to determine if the detectors
were not functioning properly unless a fire occurred.
Similar safety issues are confronted if fume hoods and pressurization
systems in laboratories do not function properly. Both provide protection
to building occupants from hazardous materials used or generated in experiments.
In one project, the pressurization control system which keeps contaminants
from leaving the lab did not work as designed because controls were not
properly calibrated. Discovering the problem would have been difficult
and more costly to resolve without commissioning, which tested the pressure
control system under many possible conditions.
top of page
Energy efficiency Many problems
found affect energy consumption — thermostats not operating correctly,
exterior air dampers that don't close properly, finned-tube radiation
elements providing heat when they should not be, fans operating too long
or running faster than they need to, or even running backwards. In addition,
HVAC systems as installed rarely offer optimum performance without fine-tuning.With
commissioning, however, energy savings can be significant, and equipment
will last longer and perform better when calibrated as designed.
top of page
Indoor air quality And because the
system has been fine-tuned and is running optimally, good indoor air quality
is maintained. Owners and facilities managers report that their phones
ring less often when the HVAC system has been commissioned. Move-in is
easier and complaints from building users are virtually eliminated.
top of page
Easier problem resolution Also, because
commissioning assesses responsibility for correcting problems before move-in
and well before the end of the warranty period, owners and managers are
less directly involved. The commissioning agent can shoulder the task
of dealing with the general contractor and subcontractors to make certain
that problems have been resolved.
Whether the benefits can be quantified through cost savings or are apparent
only because they eliminate headaches for owners and facilities managers,
commissioning keeps the links in today's complicated HVAC systems solid.
|
|
 |